UML 모델링 기반의 DBR 스케줄링 시스템 개발

Metadata Downloads
Alternative Title
Development of the DBR Scheduling System based on the UML Modeling
Abstract
Most production scheduling system in the ERP is based on the MRP. The MRP does not adapt to the change of the product design and the production schedule. It is important to keep due date in make-to-order production small and medium company. But it hard to keep due date on the MRP.
The DBR Scheduling system of the TOC is excellent for adapting to production system change and suitable to make-to-order production small and medium compan.
In this thesis, we make a system design using the Together(UML tool ) and develope a production scheduling system using Microsoft Visual Basic.Net
Author(s)
박철호
Issued Date
2007
Awarded Date
2007. 2
Type
Dissertation
Keyword
TOC DBR UML DBR 스케줄링 시스템 UML 모델링
Publisher
부경대학교 대학원
URI
https://repository.pknu.ac.kr:8443/handle/2021.oak/3480
http://pknu.dcollection.net/jsp/common/DcLoOrgPer.jsp?sItemId=000001953355
Alternative Author(s)
Park, Chul-Ho
Affiliation
부경대학교 대학원
Department
대학원 시스템경영공학과
Advisor
옥영석
Table Of Contents
제 1 장 서론 = 1
1.1 연구의 배경 및 목적 = 1
1.2 기존 연구 현황 = 2
1.3 연구내용 = 3
제 2 장 DBR과 UML = 4
2.1 동기화 경영(Synchronous Management) = 4
2.2 TOC(Theory of Constraints, 제약이론) = 5
2.2.1 드럼-버퍼-로프(Drum-Buffer-Rope: DBR) 시스템 = 7
2.3 APS = 9
2.4 UML(Unified Modeling Language) = 12
제 3 장 적용 대상 기업 분석 = 15
3.1 적용 대상 기업 생산 환경 = 15
3.2 V-A-T 분석 = 15
제 4 장 시스템 구현을 위한 UML설계 = 18
4.1 요구기능 분석 = 18
4.2 TOGETHER를 이용한 UML 작성 = 22
제 5 장 구현 시스템의 기능 및 수행 = 27
제 6 장 결론 및 향후 연구과제 = 39
참고문헌 = 40
Abstract = 42
Degree
Master
Appears in Collections:
산업대학원 > 시스템경영공학과
Authorize & License
  • Authorize공개
Files in This Item:

Items in Repository are protected by copyright, with all rights reserved, unless otherwise indicated.